From what I've read creating an automation script based on a Control ID is relatively difficult.
That being said, you could create a YORN attribute on the WORKORDER object for Complete, then create an Attribute Launch Point automation script that sets the value of the status to complete.
------------------------------
Matt McGuire
Aquitas Solutions
------------------------------
Original Message:
Sent: 07-19-2021 10:27
From: Pradeep Rout
Subject: Is there a way to change change status icon on Work Order actual screen for Task Section ?
Thanks Matt. yes i also want to change the event action to Complete instead of giving multiple option i want single action Complete
------------------------------
Pradeep Rout
TCSL
Original Message:
Sent: 07-19-2021 10:10
From: Matt McGuire
Subject: Is there a way to change change status icon on Work Order actual screen for Task Section ?
Hi Pradeep,
Change the Event Icon field in the Table Column Properties to:
nav_icon_statusComplete.gif
Are you also trying to change what the action does?
Thanks,
Matt
------------------------------
Matt McGuire
Aquitas Solutions
Original Message:
Sent: 07-19-2021 08:58
From: Pradeep Rout
Subject: Is there a way to change change status icon on Work Order actual screen for Task Section ?
Hello All,
I was doing a POC where the requirement is to change the change status icon on work order screen (Actual Tab under task sub section) to Complete workorder icon same as tool bar quick buttons.
Let me know if this is possible as i have tried in application designer and could not find a solution for this.
Thanks,
Pradeep