Hi Eric,
Thank you so much for your response. While I was expecting the fields to crossover to the PM record, I see that the constraints applied to the job plan do populate on the PM-generated work order.
Stevie
------------------------------
Stevie Holloway
Tufts University
------------------------------
Original Message:
Sent: 03-17-2022 14:22
From: Eric Godel
Subject: Job Plans Start/Finish Constraint Offset
Hello Stevie,
When you populate the Start/Finish Constraint Offset on a job plan, and when you use that job plan on a PM, the work order that is created from that PM will carry the Start/Finish Constraint from the job plan to the work order.
If both your Job Plan and PM have the constraints populated, the work order created will take the Constraints from the PM.
Hope that helps!
Eric
------------------------------
Eric Godel
Bay Systems Consulting
Original Message:
Sent: 03-17-2022 07:44
From: Stevie Holloway
Subject: Job Plans Start/Finish Constraint Offset
Hi,
When I add Start/Finish Constraint Offset to a job plan and attach it to a PM, I expect the Start/Finish Constraint Offset to populate on the PM record but this doesn't happen. Has anyone experienced this?
Thanks
#EndUser
------------------------------
Stevie Holloway