  • 1.  Job Plans Start/Finish Constraint Offset

    Posted 03-17-2022 07:44
    Hi,

    When I add Start/Finish Constraint Offset to a job plan and attach it to a PM, I expect the Start/Finish Constraint Offset to populate on the PM record but this doesn't happen. Has anyone experienced this?


    Thanks
    #EndUser

    ------------------------------
    Stevie Holloway
    Tufts University
    ------------------------------


  • 2.  RE: Job Plans Start/Finish Constraint Offset

    Posted 03-17-2022 14:23
    Hello Stevie,

    When you populate the Start/Finish Constraint Offset on a job plan, and when you use that job plan on a PM, the work order that is created from that PM will carry the Start/Finish Constraint from the job plan to the work order. 

    If both your Job Plan and PM have the constraints populated, the work order created will take the Constraints from the PM.  

    Hope that helps!
    Eric


    ------------------------------
    Eric Godel
    Bay Systems Consulting
    ------------------------------



  • 3.  RE: Job Plans Start/Finish Constraint Offset

    Posted 03-17-2022 14:36
    Hi Eric,

    Thank you so much for your response. While I was expecting the fields to crossover to the PM record, I see that the constraints applied to the job plan do populate on the PM-generated work order.



    Stevie

    ------------------------------
    Stevie Holloway
    Tufts University
    ------------------------------