Hi,
I have a meter based PM that requires a component of larger asset to be replaced every 14,000 run hours. The component is set up as a item mater and inventory record and recorded in the job plan associated to the meter based PM.
We have an integration with our scada system that automatically transfer run hour data once a day from Scada to the Maximo meter associated with the asset on the meter based PMs.
The meter based PM generates a work order and when this work order is closed the counter of hours to go until the next changed out it due resets to 0( is this how it works?)
However, in practise we sometime get an unplanned work order to replaced the component before it has reached its 14,000 hour. assume the unplanned work order is associated to the correct asset record.
How do I get this unplanned work order to automatically re start the clock on determining when the 14,000 hour based replacement is due? currently the meter based PM will forecast the wrong replacement date as the component was replaced earlier on a un planned work order