  • 1.  Reservations work order test

    Posted 01-07-2024 14:35

    Planned material on WO by default is a soft reservation, and will automatically become a hard reservation based on the target start date and material lead time

    How to test it step by step..?


    #Inventory
    #Utilities

    ------------------------------
    Samba murthy mamidala
    pwc
    ------------------------------


  • 2.  RE: Reservations work order test

    Posted 01-09-2024 01:12

    Hi Samba,

    You can try following the steps described in the automatic reservation section of this article.



    ------------------------------
    Maycon Belfort
    BPD Zenith
    ------------------------------