  • 1.  Setting the Lead Time on Meter-Based PM Work Orders

    Posted 02-26-2024 17:07

    So the scenario is:  we want to generate meter-based PMs at 80% due.

    1. Global 7-day lead time specified in the Organization settings.  HOWEVER
    2. Generate Work Order Based on Meter Readings (Do Not Estimate) is ON.  This means that the Global setting DOES NOT WORK (it's working fine for time-based PMs).
    3. So we added a value for "Generate Work Order Ahead by".
    4. Maximo generated the work order at approx. 80%, alright - but it ALSO changed the Target Start Date to the 80% mark, not the 100% mark.  This defeats the purpose of trying to add Lead Time!

    Anyone got any insight into this?  


    #WorkManagement

    ------------------------------
    Shannon Rotz
    InComm Solutions Inc.
    ------------------------------


  • 2.  RE: Setting the Lead Time on Meter-Based PM Work Orders

    Posted 02-27-2024 11:05

    Yep, we had it like this for years.  It was annoying, and we just excluded MPMs from overdue metrics.  However, last year we wrote a script to run on WO generation's Save that if WORKTYPE=MPM, to recalculate the Target Start Date something along the lines of: (PMMETER.TOLERANCE / PMMETER.AVERAGE) + GETDATE().  So now WOs can generate early enough for material planning, and there's a relatively accurate Target Start Date.  



    ------------------------------
    gail smith
    chevron
    ------------------------------



  • 3.  RE: Setting the Lead Time on Meter-Based PM Work Orders

    Posted 02-27-2024 12:54
    Thanks Gail - that's good confirmation that we haven't missed anything.  And your solution is exactly what I came up with as a possible fix, given that we can't put in a ticket for this with IBM (we're on 7.6.0.9).





  • 4.  RE: Setting the Lead Time on Meter-Based PM Work Orders

    Posted 02-29-2024 17:54

    Hi Gail and Shannon,

    This is yet another one of those things with Maximo that without observation, I never saw happening.  May I ask if this behaviour has been out through to IBM as an bug or have you raised an IBM Idea?  The issue you've raised is a bit of a fundamental thing for IBM to get right.

    Further as part of the fix for the target start date, do you also look at reframing the SNTL, FNLT, and target finish dates as all of these are centric on the target start date?



    ------------------------------
    Craig Kokay
    Principal Consultant
    COSOL

    email: craig.kokay@cosol.global
    #IBMChampion
    ------------------------------



  • 5.  RE: Setting the Lead Time on Meter-Based PM Work Orders

    Posted 03-04-2024 11:20

    Craig,

    Not sure.  I've only been working in 7.x for ~4 years now.  But considering our internal metrics have always excluded meter pms when calculating what is overdue leads me to believe it's been like this in previous versions as well.  I have not submitted anything to IBM around this.  I looked at the script and I do see the target finish is adjusted based on the new target start.  Not sure what SNTL, FNLT are.  I manage the business facing side of the application and we have a team of IT folks who execute.

    Gail



    ------------------------------
    gail smith
    chevron
    ------------------------------



  • 6.  RE: Setting the Lead Time on Meter-Based PM Work Orders

    Posted 03-05-2024 19:56

    Hi Craig:  I haven't contacted IBM, no, although I agree that would be a good thing.  We just identified this issue, first, and second, since we're on 7.6.0.9 I don't know if I have access to that portion of Support anymore (too bad - 98% of the time I can handle the issues that come up, but I sure would like IBM input on this particular one :( ).  We don't use SNTL or FNLT, so those are non-issues, but AFAIK Target Finish is still being set to Target Start Date plus Duration (although I might have to re-check that at some point too.)

    Gail:  SNTL (SNEL??) = "Start No Earlier Than", FNLT = "Finish No Later Than"



    ------------------------------
    Shannon Rotz
    InComm Solutions Inc.
    ------------------------------



  • 7.  RE: Setting the Lead Time on Meter-Based PM Work Orders

    Posted 02-27-2024 17:18

    Shannon, we run Generate WO number XX of hours ahead by using these fields. The hours ahead vary depending on asset priority and annual usage. We have ample lead time on stock ordering and downtime scheduling.

    Greg

     



    ------------------------------
    Greg Dyer
    Port Nelson Ltd
    ------------------------------



  • 8.  RE: Setting the Lead Time on Meter-Based PM Work Orders

    Posted 02-27-2024 20:29

    Hi Greg:  agreed.  But the problem is:  Maximo generates the work order 100 hours early (which is fine - that's what we want), BUT it also re-sets the Target Start Date to 100 hours early, which is NOT what we want.  Since Target Start Date is the 100% due mark, Maximo is effectively changing the schedule.  Not good!  I'll have to add an autoscript to re-set the Target Start Date back to the original 100% due mark to make this work now.



    ------------------------------
    Shannon Rotz
    InComm Solutions Inc.
    ------------------------------