Maximo Open Forum

 View Only
  • 1.  What happens when you cancel a PM Work Order

    Posted 02-23-2023 08:45

    I have a PM and a work order was canceled by someone.   Another PM was not generated and the performance was missed.  Is this normal?

    I read that the frequency is broken when a work order is canceled.  I also read that it gets reinstated.

    I've never canceled one before so don't know what I should look out for.

    Does anyone have an answer?


    #EverythingMaximo

    ------------------------------
    Wade Redd
    3rd Coast Consulting
    ------------------------------


  • 2.  RE: What happens when you cancel a PM Work Order

    Posted 03-01-2023 11:42

    Are there more than 1 PM Work Orders that got canceled? Generally, it should not be an issue in reverting the due dates when done individually. May be this has happened and you might need a fix as per given APAR.

    https://www.ibm.com/support/pages/apar/IV24986

    For now, you can generate WO manually with ignoring the frequency for the PM to happen and the adjust the next due date from Frequency tab to date when work order should generate next as per original schedule.



    ------------------------------
    Prashant Sharma
    Sedin Technologies
    Connect with me @ https://www.linkedin.com/in/psharmamaximo/

    #IBM Champion 2022
    #IBM Champion 2023
    ------------------------------



  • 3.  RE: What happens when you cancel a PM Work Order

    Posted 03-01-2023 23:06
    Thank you Prashant for your reply.
    Only 1 PM work order was cancelled.
    No subsequent PM work orders were generated. It was cancelled to work corrective work orders on the same asset. However I believe this is unrelated.
    Thoughts 

    Sent from my iPhone