Diane, I see a couple of options here . . . some requiring more keystrokes than others, so the business benefit-effort needs to be considered.
- As Frederic mentions below, you could change the 'support-assets' to rotating tools and add time for them on the Actuals tab of the work order similar to Labor
- On the 'fix-the-machine', add one or more child work orders that are associated with support-assets. The child WO(s) would be associated with the support-asset as a work order hierarch
- All actuals (time, material, etc.) charged to the child support WOs would roll up to the parent and this would create good history records to report on
- On the 'fix-the-machine' work order, add one or more job operations for the support-assets (the asset on a job operation can be different between the parent WO and the job operation).
- This would have the benefit of including support-assets time on the parent WO although the time reporting would be a labor transaction.
- Not sure of your Maximo version but you should be able to add the support-assets to the Multiple Assets and Locations table of the primary work order. The disadvantage here is that the time worked by the support-assets can't be individually tracked. This would just reflect the fact that the support-assets were related
Option one is probably the cleanest as the support-assets are truly tools. Converting to tools may require some painful master data revisions. My favorite is option two which could be implemented with existing data.
Good luck!
------------------------------
Mack Parrott
Projetech Inc.
------------------------------