  • 1.  Adding Labor and Work Log to Work Orders

    Posted 06-16-2025 06:48

    Hello all, is it possible to add Labor and Work Log Summary to a Work Order using MXWO object with MxLoader?

    Possible use case example, if I wanted to upload a site's historical data (Pre-Maximo) if it was stored in an Excel sheet?  I think this could be especially beneficial when trying to use Predict.

    1. Are there separate objects I would have to use?
    2. Would I have to create a custom object?
    3. Can I accomplish this by a relationship?

    Thank you in advance,



    ------------------------------
    Danny Richardson
    Maximo Administrator Manager
    Technimark LLC
    ------------------------------


  • 2.  RE: Adding Labor and Work Log to Work Orders

    Posted 06-16-2025 08:12
    Edited by Danny Richardson 06-16-2025 08:48

    [Update 1] I was able to achieve this by adding:

    My only issue so far is that when adding labor it is off slightly.  For example,  in MxLoader I told it to add 0:08 minutes to the work order and it added only 0:05.  (I think I have found the cause and will update once I test for anyone interested in doing this as well.)



    ------------------------------
    Danny Richardson
    Maximo Administrator Manager
    Technimark LLC
    ------------------------------



  • 3.  RE: Adding Labor and Work Log to Work Orders

    Posted 06-16-2025 08:46

    [Update 2] I was able to get the correct 8 minutes by converting the number to decimal hours:



    ------------------------------
    Danny Richardson
    Maximo Administrator Manager
    Technimark LLC
    ------------------------------



Featured Podcast
Episode 1 is live: IBM Maximo Application Suite 9.2

Watch or listen to Steven Shull and Phil Runion discuss the practical MAS 9.2 updates Maximo teams should know.

Watch the Podcast
MORE by Naviam Episode 1 cover
Watch the latest episode