How many days in advance PM / Calibration workorders are generated in Maximo. Is there any configuration setting.

  • 1.  How many days in advance PM / Calibration workorders are generated in Maximo. Is there any configuration setting.



  • 2.  RE: How many days in advance PM / Calibration workorders are generated in Maximo. Is there any configuration setting.

    Posted 06-08-2023 15:54

    PM generation depends on a variety of factors. But focusing just on the number of days in advance, there is a lead time (days) field (PM.LEADTIME) that is set on the PM to control the number of days in advance the PM will generate of when it is due. In the Organization application in the PM Options dialog, there is a "Generate WOs Due on the Current Date Plus This Number of Days" option to control how far out it goes for all PMs. These will help you control how far out in advance the PM is generated. 



    ------------------------------
    Steven Shull
    IBM
    ------------------------------



Newest Episode
Ep. 3 | Work Order Role-Based Application

Watch Steven Shull explore how Work Order Role-Based Applications in IBM Maximo can simplify work management, improve usability, and help teams focus on the right work order information.

MORE by Naviam Episode 3 cover
Watch Episode 3
Also available: Ep. 2 | Adding a QR Code to a BIRT Report