@Kevin Egolf Were you able to find the issue with these LABOR records? I am reviewing similar records in our Maximo instance, and wondering how to track down anomalies on LABOR records that don't behave as expected. Is modify availability on the PERSON record required whenever the calendar is changed?
Thank you for any help - i recognize this post is a few years old
Julia Cole
St. Louis MSD
------------------------------
Julia Cole
Metropolitan St.Louis Sewer District
------------------------------
Original Message:
Sent: 09-09-2021 12:09
From: Kevin Egolf
Subject: Labor availability in Assignment Manager
I did check that and there are no modifications to the calendar. The negative hours follow the same pattern regardless of the dates selected which seems to eliminate a spot change to the availability. This only seems to affect two of the labor records.
Kevin Egolf
kegolf@techopsolutions.net
-----------------------------------------
Director Asset Management Programs
TechOp Solutions International
Cell: 571-344-3221

Original Message:
Sent: 9/9/2021 11:35:00 AM
From: Christopher Winston
Subject: RE: Labor availability in Assignment Manager
Did you check the person record to see of the work dates were modified? Action would be Modify Person Availability.

this would cause the strange view in Assignment Manager where no work assignments are present:

------------------------------
Christopher Winston
Projetech Inc.
------------------------------