Hi @Jenna Munoz!
I don't know "Promised" Lead Time. I know Lead Time... maybe you have a custom there. If you give me more information (for example, the name field... Lead Time is INVENTORY.DELIVERYTIME).
If it is LEAD Time, it should work as you say.
Have you made the preliminary presentation and verified what date it defines there?
You can add REORDERPAD.REQUIREDATE field in "Reorder item details" to control if the problem start with "Reorder" option.
Regards!
------------------------------
Martin Fabra
ARSAT S.A. - Actively seeking employment
------------------------------
Original Message:
Sent: 04-05-2024 12:35
From: Jenna Munoz
Subject: Required by date.
I am wondering if anyone has come across the issue where an inventory item has a promised lead time of 14 days but on the PR the item required date comes up as the day you generated the auto reorder? Please let me know why this could be happening.
#Inventory
#MaximoUserGroups
#Procurement
------------------------------
Jenna Munoz
Idaho Milk Products
------------------------------