Work order schedule dates fetching wrongly when a pm work order is generated from BDI

  • 1.  Work order schedule dates fetching wrongly when a pm work order is generated from BDI

    Posted 02-10-2026 01:02
    Edited by Raj kumar 02-10-2026 01:35

    We have a meter based PM and it has a job plan. The job plan has start constraint offset as 168 and finish constraint offset as 144.

    after reaching the meter limit for an asset in the PM, the BDI has generated the work order as per schedule.

    When generated the work order the constraint dates in the work order has generated wrongly. 
    The finish no earlier than date is earlier than target finish date. 


    Can someone explain how these dates will be calculated when generating the work order from BDI


    #Administration
    #Analytics
    #Architecture
    #Assets
    #CivilInfrastructure
    #Customizations
    #EndUser
    #EverythingMaximo
    #HSE/OilandGas
    #Infrastructure
    #Integrations
    #Inventory
    #IoT
    #LifeScience/Calibration
    #Linear
    #MaximoApplicationSuite
    #MaximoForAviation
    #MaximoUserGroups
    #Mobility
    #Nuclear
    #Procurement
    #Reporting
    #Scheduling
    #Security
    #ServiceProvider
    #Spatial
    #Transportation
    #Utilities
    #WorkCenters
    #WorkManagement
    #MaximoVisualInspection
    #Predict
    #Monitor
    #Health
    #Assist
    #Safety

    ------------------------------
    Raj kumar
    Thiran Technologies
    ------------------------------



  • 2.  RE: Work order schedule dates fetching wrongly when a pm work order is generated from BDI

    Posted 02-10-2026 12:37

    That sounds like a date logic issue during work order generation rather than user input. I would double check whether the PM, Job Plan, or any automation is setting constraint dates differently than the target dates. If the finish no earlier than date is being derived separately, it could explain why it ends up earlier than the target finish.



    ------------------------------
    Lucas Pletz
    Naviam
    ------------------------------



Newest Episode
Ep. 6 | Automation Script Do’s and Don’ts in IBM Maximo

Watch Steven Shull share practical do’s and don’ts for using automation scripts in IBM Maximo, including when scripts make sense, what to avoid, and how to keep them simple, tested, documented, and supportable.

MORE by Naviam Episode 6 cover
Watch Episode 6
Also available: Ep. 5 | Make Manage Feel Like Home with Configuration, Not Customization