Experts,
Is this PM sequence a candidate for Maximo Job Plan sequencing? This is a meter-based PM. Job plans will be rewritten to incorporate previous JP tasks where needed.
The initial PM will fire PM/Job Plan 1960 at meter reading 1,000
Then, when the meter reading reaches 2,000, we need JP 1961 to generate
Then, when the meter reading reaches 3,000, generate JP 1960 again
When the meter reads 4000, generate JP 1962
At 5,000, generate 1960 again
Then at 6,000 generate 1961 again
At 7,000 generate 1960 again
At 8,000, generate 1963
Thoughts on this? Ideas?