Maximo Open Forum

 View Only

 Route Child work orders target start dates

  • Scheduling
  • Work Management
Taran Medcalf's profile image
Taran Medcalf posted 11-25-2023 16:06
Hi,


When using a route on a pm record to generate child work orders, can the target start date of each child work order be set to match the target finish date of the preceding child work order?

I am hoping to create a set of target start dates and target finished dates that show that each child work order is finished one after the other


In addition, can the target start date and the target finish date of the parent work order be set to match the TSD of the 1st child work order and the TFD of the last child work order?

If all this works i want to applie offset contraints to the parent work order to indicate the acceptable time window to complete the package of all child work orders

Regards
Taran

Prashant Sharma's profile image
Prashant Sharma

Hello - If your route creates Task Work Orders for route stop then flow control feature can be used.

https://www.ibm.com/support/pages/work-order-flow-control-release-71