 Yearly forecast for several PM

  • Scheduling
Fredrik Roos's profile image
Fredrik Roos posted 04-22-2024 10:20

Hello, 

I am trying to get control of our PM planning for the next year. When I make a forecast I can only see it for one PM. 

I would like to see a yearly forecast for all our PMs in different areas in the Factory.  For example we have 32 PMs in one area that I would like to make a forecast for all together for next year.

Thanks for all input in this matter. 

BR Fredrik Roos, 

Shannon Rotz's profile image
Shannon Rotz

There's a cron task that comes with Maximo, but isn't enabled.  It will run the forecasts for all of the active PMs at whatever interval you choose.  Actually, there are two cron tasks - one to run the forecasts, and the other to run the forecasts costs, if your Job Plans have Labor, services and materials on them.

If your PMs have floating schedules, i.e. the "Use Target Start Date" flag is off, then you also probably want to tell Maximo to re-forecast automatically when the work order is completed.  That option is available in the Organization screen.