Good morning, Cheryl
Have you considered entering into a Purchase Contract with a payment schedule? You can define the payment schedule as 10% on approval of the PO, then the rest on receipt of the item. So, you approve the contract, then go and do the PO. When the PO is approved, an invoice for 10% of the cost is generated. When you then get the goods in and receive them, the other 90% is then paid.
So, let's talk about what didn't happen. If you didn't set an end date for the contract, or there is still time to reach the end date, the contract doesn't expire when you receive all the items on the contract. Meaning that you can place more POs for that item from the contracted vendor until the contract either is closed or expires.
It's down to a bit of interpretation for the purchase contract (Type = Purchase) whether it should be expired.
As an example, I create a purchase contract to buy 1 x snow shovel @ $1,300. I subsequently place a PO and receive that shovel, therefore fulfilling the contract. Yet because Maximo didn't automatically expire the contract, I can continue to purchase 1 x snow shovel @ $1,300.
If this is an issue for your business, then an automation script or/and escalation could be created to expire the contract. Alternatively, you can do this as part of a manual review.
------------------------------
Craig Kokay
Principal Consultant
COSOL
email:
craig.kokay@cosol.global#IBMChampion
------------------------------