There are times when I have to cancel a single Work Order due to valid reasons (yesterdays shift cancellation due to a blizzard). I get the warning
"BMXAA8231I - If you cancel the work order, the preventive maintenance record is not reinstated. Do you want to continue?"
Because we generate Work Orders 42 days in advance and this is a single daily PM Work Order, I assume this will have no impact because I do not want this Work Order re-generated? We already have numerous daily Work Orders generated and the Estimated next due date is well established.
Am I interpreting this correctly? I do occasionally have to cancel and entire series of WO's and I have entered a new "Extended Date" and checked "Adjust Next Due Date?" to make the entire series recreate.
#WorkManagement------------------------------
Charlie Dearborn
Maintenance Planner/Scheduler
Abbott Laboratories
Scarborough, ME
------------------------------